Through our Tier 1 facilities management customer, we delivered mechanical installation and project works to one of their clients, the worlds’ largest provider of flexible workspace solutions with 3000 business centres spanning almost 900 cities.
Our installation project was delivered to a large contemporary business centre of circa 5000m² over four floors in Edinburgh providing 24/7 secure access, staffed reception with call answering, high-speed telecoms, well-equipped kitchen areas, 5 meeting rooms and onsite parking for permanent and hot desk clients.
The scope of works involved like-for-like replacement of two existing ageing boilers with new and all necessary modifications and improvement to plant room. Existing gas boilers were at least fifteen years old. phs Compliance worked closely with our partner and leading heating solutions provider Remeha across design and commissioning project phases. phs Compliance completed all pressure and system testing for site.
Access to boilers and the third-floor plant room was only available via a rear stairwell and a single frame door. Since physical access was highly restrictive, boilers had to be disassembled, broken down, built and installed in situ, using a battery-powered stair walker along with extensive manual handling of components.
Existing flues were not compatible with the new installations, so new flues were installed alongside precise pipework modification and hot works carried out in situ to ensure the existing pipework remained compliant and functional. New burners extended the front fascia of the boiler housing, so to optimise subsequent planned maintenance activities, phs Compliance engineers rerouted pipework from the water tank to meet the new Riello RS70M burner requirements.
Throughout the boiler replacement works, heating services had to be maintained. At the time of these works, Scotland’s central belt region had over 15 cm of snow and ice on the ground and ambient daytime temperatures of -8°C. Each Remeha P420/10 boiler was installed individually, ensuring a minimum changeover period, and weekend working limited the potential for disruption to normal business operations. An area of car park to the rear of the property was cordoned off for site works, skips, deliveries and for the use of a cherry picker to install new flues.
The key short term benefit for our client lies in significantly improved asset reliability, with associated cost reduction in reactive maintenance and spare parts. Annual gains in energy efficiency are also valuable – with forecast 10% improvement in heating efficiency equating to around £2k per annum, our client can anticipate saving more than £30k over the lifetime of the new Remeha boilers.
Minimising commercial electrical faults should be a priority for any business. Why? Because they can put your employees and equipment at risk and cause unplanned, costly downtime. What’s more,
If the main power supply in your building fails for any reason, your emergency lighting is there to provide on-site safety. Emergency light types, including escape route and open-area lighting, are
With so many regulations and sources of advice available, it can be hard for organisations to distinguish between statutory legal compliance and best practice. “Recommended”, “required”, and
Whether you manage a public sector building or have a large residential portfolio, understanding your legal obligations as a facility manager is essential. You have a duty of care to keep your
This site uses cookies that enable us to make improvements, provide relevant content, and for analytics purposes. For more details, see our Cookie Policy. By clicking Accept, you consent to our use of cookies.